As a PM, I can control work packages assignments

Project Managers (PM), and other managers (PMA, PMO, PfM, and PgM), can control work package assignments by navigating to CONTROL → Control Resources → Assignments or at CONTROL > Control Resources > Resources.

The Assignments and Resources page provides two tabs:

  • Team Members
  • Material Resources

Select the appropriate tab depending on the type of resource you want to review or update. Then select the resource and the associated work package to view its assignment details.

Team Member Assignments

Select the Team Members tab to review and control team member assignments.

First, select a Team Member, and then select the associated Work Package.

Project Managers (PM) can update the following fields:

  • Planned Start: Project manager’s best estimate for this team member to start working on this work package.
  • Planned Finish: Project manager’s best estimate for this team member to finish working on this work package.
  • Planned Work (h): Project manager’s best estimate for effort hours for this team member on this work package.

Team Members (TM) can see these fields when reviewing their assignments (see 2.1.2.6).

The other fields are read only. The first three can be updated at PLAN > Plan Resources > Assign Team Members or at PLAN > Plan Resources > Assign Work Packages:

  • Baseline Start: Committed date for this team member to start working on this work package.
  • Baseline Finish: Committed date for this team member to finish working on this work package.
  • Baseline Work (h): Committed effort hours for this team member on this work package.
  • Actual Work (h): Effort hours submitted by the team member and approved by project manager up to date.
  • Actual Work Cost: Calculated as actual hours * team member’s cost rate.
  • Actual Work Billable: Calculated as actual hours * team member work package’s selling rate.
  • Actual Expenses: Expenses submitted by the team member and approved by project manager up to date.

Material Resource Assignments

Project Managers (PM) can update the following fields:

  • Planned Start: Project Manager’s best estimate for when this material resource will start being used in the selected work package.
  • Planned Finish: Project Manager’s best estimate for when this material resource will finish being used in the selected work package.
  • Planned Units: Project Manager’s best estimate of the quantity of this material resource required for the selected work package.

The remaining fields are read-only.

  • Baseline Start: Committed date for this material resource to start being used in this work package.
  • Baseline Finish: Committed date for this material resource to finish being used in this work package.
  • Baseline Units: Committed quantity of this material resource required for this work package.
  • Used Units: Quantity of the material resource that has been consumed or recorded as used for this work package.
  • Actual Cost: Calculated based on the used units and the material resource cost rate.
  • Description: Additional information about the material resource assignment.

Project Managers (PM) can also edit assignment details with the mobile application. Once they have entered any organization (for instance, DEMO PMPeople), they need to select the role Project Manager, then the concrete project and finally, hit the menu option Control Resources > Control Assignments:

As a PMO, PfM, PgM, PM, RQ, PMA, SP, I can notify by email if there is some change, by clicking the button [Notify].

Frequently Asked Questions

Q: How can a project manager control work package assignments in PMPeople?
A: Project managers can control assignments from Control > Control Resources > Assignments or Resources, by selecting a work package or a resource (team member or material resource) to update planned estimates.

Q: What fields can project managers update in work package assignments?
A: Project managers can update the planned start date, planned finish date, and planned work (hours). Reference and actual values ​​are read-only in the CONTROL section and editable in the PLAN section.

Q: Can project managers notify team members about changes to assignments?
A: Yes, after updating assignment details, project managers can use the [Notify] button to send assignment updates to team members via email.